Default Asbestos Abatement/Reclamation questions

Replacing all of the flooring in our place. House is 30 years old and has original asbestos tile that has a subfloor over top and then lino in both main floor bathroom and upstairs bathroom. Entrance foyer and entire kitchen.

Abatement company coming in for 8 days to deal with removing all layers.
Flooring replacement will begin after the abatement.

We need to vacate and can not return for any reason for the duration. Fridge, stove, dishwasher and toilets and all furniture all wall décor have to be removed before Abatement company arrives

I have been emptying the entire house into the basement and was just starting to empty the content of all the kitchen cupboards, pantry, pots, pans etc-A huge job, but the abatement company point man is advising that the cupboard contents can be left as is in place, as they will all be totally sealed with poly before they begin.

This makes me really nervous.

Does anyone have first hand knowledge or been through this before?
__________________
You're only as good as your last haircut
Reply With Quote
  #2  
Old 10-04-2017, 06:43 PM
bat119's Avatar
bat119 bat119 is offline
 
Join Date: Jan 2012
Location: On the border in Lloydminster
Posts: 8,369
Default

Everything will be taped and plastic sealed then the coverings will be sprayed with sticky substance to catch any airborne particles. The plastic will be removed after the job is done double bagged and disposed off. As long as the job is properly done it wont be a problem.
__________________
Si vis pacem, para bellum
Reply With Quote
  #3  
Old 10-04-2017, 06:45 PM
Weedy1 Weedy1 is offline
Banned
 
Join Date: Dec 2007
Location: Edmonton
Posts: 2,485
Default

Have you had your tile independently tested? Seems rather odd to have asbestos tile in a 30 year old home. Lots of labs that will test for $50.
I hope your not getting conned.
Reply With Quote
  #4  
Old 10-04-2017, 06:46 PM
omega50's Avatar
omega50 omega50 is offline
 
Join Date: Dec 2009
Posts: 8,497
Default

Quote:
Originally Posted by bat119 View Post
Everything will be taped and plastic sealed then the coverings will be sprayed with sticky substance to catch any airborne particles. The plastic will be removed after the job is done double bagged and disposed off. As long as the job is properly done it wont be a problem.

Is all of the wall and ceiling surface area typically sealed off as well? Popcorn ceiling.
__________________
You're only as good as your last haircut
Reply With Quote
  #5  
Old 10-04-2017, 06:50 PM
bat119's Avatar
bat119 bat119 is offline
 
Join Date: Jan 2012
Location: On the border in Lloydminster
Posts: 8,369
Default

Quote:
Originally Posted by omega50 View Post
Is all of the wall and ceiling surface area typically sealed off as well? Popcorn ceiling.
Yes all the walls ceiling or anything that's staying will be taped off. I did asbestos removal on commercial building and industrial boilers ducts etc. for 10 years.
__________________
Si vis pacem, para bellum
Reply With Quote
  #6  
Old 10-04-2017, 06:51 PM
omega50's Avatar
omega50 omega50 is offline
 
Join Date: Dec 2009
Posts: 8,497
Default

Quote:
Originally Posted by Weedy1 View Post
Have you had your tile independently tested? Seems rather odd to have asbestos tile in a 30 year old home. Lots of labs that will test for $50.
I hope your not getting conned.
We are not bearing the cost-It has been independently confirmed.
Unfortunate , but true,

Apparently that the company also has to be monitored by independent third party during abatement
__________________
You're only as good as your last haircut

Last edited by omega50; 10-04-2017 at 07:01 PM.
Reply With Quote
  #7  
Old 10-04-2017, 07:00 PM
bat119's Avatar
bat119 bat119 is offline
 
Join Date: Jan 2012
Location: On the border in Lloydminster
Posts: 8,369
Default

Quote:
Originally Posted by Weedy1 View Post
Have you had your tile independently tested? Seems rather odd to have asbestos tile in a 30 year old home. Lots of labs that will test for $50.
I hope your not getting conned.
Asbestos was banned starting in 60's & 70's however some was considered "low risk" such as in floor tiles and building siding because the particles weren't as large and it was thought they didn't pose a hazard by 1984 they were banned as well. Contractors bought huge stock piles at fire sale prices after the ban and continued to install it well after the ban. Always check to be sure.
__________________
Si vis pacem, para bellum
Reply With Quote
  #8  
Old 10-04-2017, 07:04 PM
omega50's Avatar
omega50 omega50 is offline
 
Join Date: Dec 2009
Posts: 8,497
Default

Quote:
Originally Posted by bat119 View Post
Asbestos was banned starting in 60's & 70's however some was considered "low risk" such as in floor tiles and building siding because the particles weren't as large and it was thought they didn't pose a hazard by 1984 they were banned as well. Contractors bought huge stock piles at fire sale prices after the ban and continued to install it well after the ban. Always check to be sure.
Timeline is right and I believe built in 83- 84 ish
__________________
You're only as good as your last haircut
Reply With Quote
  #9  
Old 10-04-2017, 07:12 PM
bat119's Avatar
bat119 bat119 is offline
 
Join Date: Jan 2012
Location: On the border in Lloydminster
Posts: 8,369
Default

I was working on a potash mine installing Asbestos siding in 1984 when the ban came in they told us to do all the cutting outside (skilsaw). After that job was over the company I worked started removing asbestos.
__________________
Si vis pacem, para bellum
Reply With Quote
  #10  
Old 10-04-2017, 07:24 PM
The Cook The Cook is offline
 
Join Date: Jun 2014
Location: Canmore
Posts: 2,105
Default

A friend bought an old house in town and had a company come in and he was impressed with the job done. With something like asbestos it's best to use the pros.
__________________
Woke up with a pulse, best day ever
Reply With Quote
  #11  
Old 10-04-2017, 07:24 PM
omega50's Avatar
omega50 omega50 is offline
 
Join Date: Dec 2009
Posts: 8,497
Default

Quote:
Originally Posted by bat119 View Post
I was working on a potash mine installing Asbestos siding in 1984 when the ban came in they told us to do all the cutting outside (skilsaw). After that job was over the company I worked started removing asbestos.
Thanks for sharing your knowledge.

AO is perhaps the deepest well of knowledge in the universe.
__________________
You're only as good as your last haircut
Reply With Quote
  #12  
Old 10-04-2017, 07:34 PM
bat119's Avatar
bat119 bat119 is offline
 
Join Date: Jan 2012
Location: On the border in Lloydminster
Posts: 8,369
Default

I should mention during the job a negative air filter unit will be installed creating a light vacuum in the house if there any small tears or holes in the hoarding air will be sucked in as not to release fibers.
__________________
Si vis pacem, para bellum
Reply With Quote
  #13  
Old 10-04-2017, 07:55 PM
omega50's Avatar
omega50 omega50 is offline
 
Join Date: Dec 2009
Posts: 8,497
Default

Quote:
Originally Posted by bat119 View Post
I should mention during the job a negative air filter unit will be installed creating a light vacuum in the house if there any small tears or holes in the hoarding air will be sucked in as not to release fibers.
How do they deal with fresh air returns and floor registers in those rooms? Do they need to shut down the furnace?
__________________
You're only as good as your last haircut
Reply With Quote
  #14  
Old 10-04-2017, 08:12 PM
bat119's Avatar
bat119 bat119 is offline
 
Join Date: Jan 2012
Location: On the border in Lloydminster
Posts: 8,369
Default

Quote:
Originally Posted by omega50 View Post
How do they deal with fresh air returns and floor registers in those rooms? Do they need to shut down the furnace?
They will cover them when they are working usually hoarding off the affected areas as small as they can. A manometer while be installed to monitor air pressure if they reading drops they know they have a leak. They don't want particles in the HVAC systems.
__________________
Si vis pacem, para bellum
Reply With Quote
  #15  
Old 10-04-2017, 09:01 PM
coastalhunter coastalhunter is offline
 
Join Date: Jun 2014
Location: Peace River, BC
Posts: 630
Default

We do it in an industrial environment at work. Literally spend weeks building the hoardings and testing them prior to abatement.
Reply With Quote
  #16  
Old 10-04-2017, 09:07 PM
wildbill wildbill is offline
Banned
 
Join Date: Jun 2011
Location: Gods Country
Posts: 1,706
Default

Quote:
Originally Posted by bat119 View Post
I should mention during the job a negative air filter unit will be installed creating a light vacuum in the house if there any small tears or holes in the hoarding air will be sucked in as not to release fibers.
Aint required, tile removal is text book low risk, neg air are for high risk. I've removed floor tile and the readings were so low that in theory we could done it with out RPE as the levels were way below the 8 hour OEL. I don't think this abatement company would go above and beyond OH&S regs and use a neg air but you never know. Omega, the important question is will there be independent air monitoring done? There better be, you can refer to the levels after the removal (there should be background air monitoring prior to the removal so the consultant can get their base line). The consultant should be able to explain it to you. If the abatement company who is doing the removal are the ones doing the air monitoring, I would be extremely worried as the would be a huge conflict of interest, and may mean they may be taking shortcuts. Over all tile removal is no big deal, unless they start hackin her out. Anytime you start mechanically disturbing asbestos tile it then becomes high risk (ie.drilling, die grinding, zip cutting ect). Hope that helps
Reply With Quote
  #17  
Old 10-04-2017, 09:20 PM
wildbill wildbill is offline
Banned
 
Join Date: Jun 2011
Location: Gods Country
Posts: 1,706
Default

Sorry didn't see post #6, so there will be a consultant, if it's someone like Ben and his crew from Golder you will be in good hands and they will ensure proper procedure is followed
Reply With Quote
  #18  
Old 10-04-2017, 09:26 PM
bat119's Avatar
bat119 bat119 is offline
 
Join Date: Jan 2012
Location: On the border in Lloydminster
Posts: 8,369
Default

We used Neg air units and hoarding because after the tile was removed the substrate was drum sanded. We did stores and offices as well as industrial equipment.
__________________
Si vis pacem, para bellum
Reply With Quote
  #19  
Old 10-04-2017, 09:33 PM
omega50's Avatar
omega50 omega50 is offline
 
Join Date: Dec 2009
Posts: 8,497
Default

They are taking it down to substrate. Will there typically be some wall damage as I am going to repaint the entire house, but will wait until after abatement if wall damage is a possibility
__________________
You're only as good as your last haircut
Reply With Quote
  #20  
Old 10-04-2017, 09:41 PM
wildbill wildbill is offline
Banned
 
Join Date: Jun 2011
Location: Gods Country
Posts: 1,706
Default

What does it say on their APN (asbestos project notification) it will state whether it's low, med,or, high, if they are bat sanding then ya can even expect a visit from an oh&s officer as it would be high risk.
Reply With Quote
  #21  
Old 10-04-2017, 09:56 PM
CaberTosser's Avatar
CaberTosser CaberTosser is offline
 
Join Date: Aug 2007
Location: Calgary
Posts: 19,420
Default

As you noted the abatement crew does have another independent company that performs the air monitoring. I've had abatement performed for jobs prior to boiler replacements where the pipe insulation had ACM (asbestos containing material) as well as one where the drywall mud had asbestos and we needed some holes in a hallway ceiling. The biggest one though was my Dad's former commercial property where he spent about a half a million getting abatement performed from the insulation packed onto the ceiling of the quonset roof of the warehouse around 20 years ago.
__________________
"The trouble with people idiot-proofing things, is the resulting evolution of the idiot." Me
Reply With Quote
  #22  
Old 10-18-2017, 01:09 PM
omega50's Avatar
omega50 omega50 is offline
 
Join Date: Dec 2009
Posts: 8,497
Default

Yikes- very shoddy work.
They finished yesterday and I did the walkthrough today.

Huge mess under the basement stairs all over our storage items-They coming back Saturday to individually remove and clean all items-Idiots
__________________
You're only as good as your last haircut
Reply With Quote
  #23  
Old 10-18-2017, 02:44 PM
tchammer's Avatar
tchammer tchammer is offline
 
Join Date: Nov 2013
Posts: 423
Default

Welcome to the biggest construction scam of all time. If they continue down this road it will be a disaster. Just about every single house built before around 1980 had asbestos in the linoleum backing. And just about every single house built up to that time has linoleum somewhere underneath. Start doing the math and see how much this will cost the tax and insurance payer, which is all of us, and it is staggering. And all for the benefit of a very small controlled group of companies that remove asbestos "safely". It's a joke.
Reply With Quote
Reply


Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump


All times are GMT -6. The time now is 12:52 AM.


Powered by vBulletin® Version 3.8.5
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.