Originally Posted by Ken07AOVette View Post
I had the floor poured already so I built them on perfect level, and a forklift to stand the walls up (nice little cheat)

I did have help, couple friends here and there when needed. It really was not rocket science, and 4 walls aren't that hard to frame in a day, 2 big doors meant a lot of nothing to do, 40' walls were 2 piece and 50's were 3 iirc.
Yeah, framing 4 walls that size in a day is doable. But I would allow a half day for one guy to cut 160 odd studs, cut the headers and trimmers and nail them all together. Leaving less than half a day for trusses, ladders, fascia,sheeting, porkchops, garage door liners, installing man doors, overhead doors..... That's a real solid two days work IMO.